RAIL – Australian Utility Solutions https://web.adns.run Specialist Utilities Management Consultancy Tue, 12 Oct 2021 05:12:17 +0000 en-US hourly 1 https://wordpress.org/?v=5.8 ../../../../wp-content/uploads/2021/08/favicon.jpg RAIL – Australian Utility Solutions https://web.adns.run 32 32 Parramatta Light Rail – Stage 1 ../../../../parramatta-light-rail-stage-1/ Thu, 05 Aug 2021 04:03:40 +0000 https://web.adns.run/?p=1119 Parramatta Light Rail – Stage 1 Read More »

]]>

Parramatta Light Rail – Stage 1

PROJECT SUMMARY

LENGTH
12 kms
STATIONS
16 x stations
TRAMS
Urbos 3s

UTILITY TREATMENTS

MAIN WORKS
circa 1,300 relocations
ENABLING WORKS
circa 60 relocations

UTILITY AUTHORITIES

Ausgrid & Endeavour Energy
Sydney Water
Jemena, Caltex, Viva
Telstra, Optus, NBN, TPG
Sydney Trains
RMS
Council

KEY UTILITIES

Potable Water: 2 x1200mm diameter
Wastewater: 1200mm diameter
Fuel: Viva 7,000kPa
Gas: Jemena HP 1,050kPa High Pressure
Electrical: incl. 132, 66 & 33kV Transmission & Substations
Comms: incl. 720 pair fibres, 1000pr copper

AT A GLANCE

Client: Transport for NSW 
Project Value: $2.4bn                  
AUS Start: Aug 2016
AUS Finish: Ongoing
AUS Role: Utilities Management
AUS Team: (5 x utility specialists) Utilities Lead + 3 x Utilities Area PM’s + GIS  
Works: 1300 + 60 utility treatments 

AUS ROLE

AUS has overall responsibility for the management of utilities on behalf of TfNSW. Our commission started with Business Case, through procurement including Tender Negotiations/Contract Award and has continued through Construction. Our Scope included defining the utilities scope, undertaking utility concept designs, 12d modelling, the creation and management of a Utilities GIS, Constructability reviews and staging plans, preparation of Tender Estimates and Utilities Programs and during delivery Contract Admin, Design & Constructability Reviews and claims advice.

Description of Service Scope:

  • Utilities Project Management & Coordination
  • Utility Clash Assessment (Registers & Drawings)
  • Utility Digital Engineering GIS’s & 12D
  • Preparing the Utilities Survey Scope (PS321) and management through G71 
  • Utility Constructability & Staging advice including during delivery
  • Utilities Designs (Contestable – Water & Electrical) & Option Papers, including obtaining Scope of Works and Letters of Offer for the utility Authority
  • Preparation of Utility Tender Estimates and Utility Construction Programs 
  • Interdisciplinary designs reviews 20, 50, 80, 100%
  • Preparing and updating the Utilities Management Plan
  • Utilities Transaction, Contract & Delivery advice
  • Utility Specifications for inclusion in Tender/Contract
  • 3rd Party Utility Agreement advice & Interface Management during Construction
  • Property acquisition and Easements planning & advice
  • Early/Enabling Works Scoping & Management
  • Utilities Contract Administration & Claims Management
  • Traction Power Supply Agreements
]]>
Parramatta Light Rail – Stage 2 ../../../../parramatta-light-rail-stage-2/ Thu, 05 Aug 2021 04:25:33 +0000 https://web.adns.run/?p=1138 Parramatta Light Rail – Stage 2 Read More »

]]>

Parramatta Light Rail – Stage 2

PROJECT SUMMARY

LENGTH
9 kms 
STATIONS
15 x stations 
TRAMS
tbc

UTILITY TREATMENTS

MAIN WORKS
tbc
ENABLING WORKS
tbc

UTILITY AUTHORITIES

Ausgrid
Endeavour Energy
Sydney Water
Jemena, Caltex, Viva
Telstra, Optus, NBN, TPG
Sydney Trains
RMS
Council

KEY UTILITIES

Potable Water: 2 x1200mm diameter
Wastewater: 1200mm diameter
Fuel: Viva 7,000kPa
Gas: Jemena 1,050kPa High Pressure
Electrical: incl. 33kV Transmission & Substations
Comms: incl. 720 pair fibres

AT A GLANCE

Client: Transport for NSW (TfNSW)
Project Value: TBC
AUS Start: Apr 2017
AUS Finish: Ongoing
AUS Role: Utilities Management
AUS Team: (3 x utility specialists) = Utilities Lead + 1 x Area PM’s + GIS   
Works: tbc

AUS ROLE

Description of Service Scope:

AUS has overall responsibility for the management of utilities on behalf of TfNSW for the preparation of the Final Business Case. Our Scope includes defining the utilities scope, undertaking utility concept designs, the creation and management of a Utilities GIS, Constructability reviews and staging plans, preparation of Tender Estimates and Utilities Programs.

  • Utilities Project Management & Coordination
  • Utility Clash Assessment (Registers & Drawings)
  • Utility Digital Engineering GIS’s & 12D
  • Preparing the Utilities Survey Scope (PS321)
  • Utility Constructability & Staging advice
  • Utilities Concept Designs
  • Peer Review of  Utility Tender Estimates
  • Preparing Utility Construction Programs 
  • Interdisciplinary designs reviews 
  • Preparing and updating the Utilities Management Plan
  • 3rd Party Utility Agreement advice
  • Property acquisition and Easements planning & advice
  • Early/Enabling Works Scoping
]]>
Sydney CBD and South East Light Rail ../../../../sydney-cbd-and-south-east-light-rail/ Thu, 05 Aug 2021 03:38:09 +0000 https://web.adns.run/?p=1099 Sydney CBD and South East Light Rail Read More »

]]>

Sydney CBD and South East Light Rail

PROJECT SUMMARY

LENGTH
12 kms
STATIONS
19 x stations
TRAMS
Alstom Citidus (60m)

UTILITY TREATMENTS

MAIN WORKS
circa 2,300 relocations
ENABLING WORKS
circa 50 relocations

UTILITY AUTHORITIES

Ausgrid
Sydney Water
Jemena
Telstra, Optus, NBN, TPG
Sydney Trains
RMS & Council

KEY UTILITIES

Electrical: incl. 132kV Transmission, Substations & Ausgrid Triplex Network
Potable Water: 1200mm diameter
Wastewater: Tank Stream
Gas: Jemena HP 1,050kPa High Pressure
Comms: incl. 720 pair fibres optic cables

AT A GLANCE

Client: Transport for NSW 
Project Value: $2.1bn 
AUS Start: Oct 2015
AUS Finish: Ongoing
Role: Utilities Management
AUS Team: (5 x utility specialists) = Utilities  Lead + 3 x Utilities Area PM’s + Utilities Cost Manager       
Works: 2,300 utility treatments

AUS ROLE

AUS was responsible for the management of utilities on behalf of TfNSW on what many consider to be the most complex utility project undertaken in NSW. Our commission started through procurement including Tender Negotiations/Contract Award and has continued after Construction. Our Scope included pulling together the utilities scope (defined by others), the creation and management of a Utilities GIS, Constructability reviews and staging plans, preparation of Tender Estimates and Utilities Programs and claims advice.

Description of Service Scope:

  • Utilities Project Management & Coordination
  • Managing the TA undertaking the Utility Clash Assessment
  • Utility Digital Engineering GIS
  • Utility Constructability & Staging advice
  • Obtaining Utility Tender Estimates and Utility Construction Programs 
  • Preparing and updating the Utilities Management Plan
  • Utilities Transaction, Contract & Delivery advice
  • Property acquisition and Easements planning & advice
  • Early/Enabling Works Management
  • Utilities Contract & Claims Management
  • Traction Power Supply Agreements
  • Stakeholder Management during construction
]]>
Newcastle Light Rail ../../../../newcastle-light-rail/ Mon, 26 Jul 2021 04:11:42 +0000 https://utilitysolutions.flywheelsites.com/?p=659 Newcastle Light Rail Read More »

]]>

Newcastle Light Rail

PROJECT SUMMARY

LENGTH
2.7 kms
STATIONS
6 x stations
TRAMS
Urbos 100 x 33m

UTILITY TREATMENTS

MAIN WORKS
circa 130 Relocations

UTILITY AUTHORITIES

Ausgrid
Hunter Water
Jemena
Telstra, Optus, NBN, TPG
Sydney Trains
RMS & Council

KEY UTILITIES

Potable Water: 1200mm diameter
Wastewater: 3000mm x 1220mm
Gas: Jemena HP 1,050kPa
Electrical: incl. 11kV High
Voltage OH & UG, Substations
Comms: incl. 244 pair fibres

AT A GLANCE

ClientTransport for NSW 
Project Value: $260m  
AUS Start: Dec 2015 
AUS Finish: Feb 2016
AUS Role: Utilities Management 
AUS Team: Utilities Lead + GIS

Works: 130 utility treatments  60

AUS ROLE

AUS has overall responsibility for the management of utilities on behalf of TfNSW. Our commission started through procurement including Tender Negotiations/Contract Award and continued through Construction. Our Scope included pulling together the utilities scope (defined by others), the creation and management of a Utilities GIS, Constructability reviews and staging plans, preparation of Tender Estimates and Utilities Programs and claims advice and managing the Technical Advisor.

Description of Service Scope:

  • Utilities Project Management & Coordination 
  • Utility Clash Assessment (Registers & Drawings) 
  • Utility Digital Engineering GIS 
  • Utility Constructability & Staging advice 
  • Utilities Designs (Contestable – Water & Electrical) & Option Papers
  • Obtaining Scope of Works and Letters of Offer for the utility Authority 
  • Obtaining Utility Tender Estimates and Utility Construction Programs 
  • Preparing and updating the Utilities Management Plan  
  • Utilities Transaction, Contract & Delivery advice 
  • Utility Specifications advice 
  • 3rd Party Utility Agreement advice & Interface Management during Construction 
  • Property acquisition and Easements planning & advice 
  • Utilities Contract & Claims Management 
]]>